Modifier and Type | Field and Description |
---|---|
static Key<NullableBool,Integer> |
ACTUALS_IN_SYNC
Determines whether all actual works have been synchronized with the project.
|
static Key<NullableBool,Integer> |
ADMIN_PROJECT
Determines whether a project is an administrative project.
|
static Key<NullableBool,Integer> |
ARE_EDITABLE_ACTUAL_COSTS
Determines whether actual costs are editable.
|
static Key<String,Integer> |
AUTHOR
The author of a project.
|
static Key<NullableBool,Integer> |
AUTO_ADD_NEW_RESOURCES_AND_TASKS
Determines whether new resources or tasks automatically added to a resource or task pool.
|
static Key<NullableBool,Integer> |
AUTOLINK
Determines whether inserted or moved tasks are auto linked.
|
static Key<Integer,Integer> |
BASELINE_FOR_EARNED_VALUE
The specific baseline used to calculate Variance values.
|
static Key<Calendar,Integer> |
CALENDAR
The project calendar.
|
static Key<String,Integer> |
CATEGORY
The category of a project.
|
static Key<String,Integer> |
COMMENTS
Project's comments.
|
static Key<String,Integer> |
COMPANY
The company where a project was created.
|
static Key<Date,Integer> |
CREATION_DATE
The date and time when a project was created.
|
static Key<Integer,Integer> |
CRITICAL_SLACK_LIMIT
The number of days to the end of a task when Microsoft Project
marks that task as a critical task.
|
static Key<String,Integer> |
CURRENCY_CODE
The three letter currency character code as defined in ISO 4217.
|
static Key<Integer,Integer> |
CURRENCY_DIGITS
The number of digits after a decimal symbol.
|
static Key<String,Integer> |
CURRENCY_SYMBOL
The currency symbol used in a project.
|
static Key<Integer,Integer> |
CURRENCY_SYMBOL_POSITION
The placement of the currency symbol.
|
static Key<Date,Integer> |
CURRENT_DATE
The system date.
|
static Key<String,Integer> |
CUSTOM_DATE_FORMAT
Project view custom date format.
|
static Key<Integer,Integer> |
DATE_FORMAT
Project view date format.
|
static Key<Integer,Integer> |
DAYS_PER_MONTH
The number of days per month.
|
static Key<Date,Integer> |
DEFAULT_FINISH_TIME
The default finish time of new tasks.
|
static Key<Integer,Integer> |
DEFAULT_FIXED_COST_ACCRUAL
The default type when fixed costs are accrued.
|
static Key<Double,Integer> |
DEFAULT_OVERTIME_RATE
The default overtime rate for new resources.
|
static Key<Double,Integer> |
DEFAULT_STANDARD_RATE
The default standard rate for new resources.
|
static Key<Date,Integer> |
DEFAULT_START_TIME
The default start time of new tasks.
|
static Key<Integer,Integer> |
DEFAULT_TASK_EV_METHOD
The default earned value method for tasks.
|
static Key<Integer,Integer> |
DEFAULT_TASK_TYPE
The default type of new tasks.
|
static Key<Integer,Integer> |
DURATION_FORMAT
The format for expressing the bulk duration.
|
static Key<Integer,Integer> |
EARNED_VALUE_METHOD
The default method for calculating earned value.
|
static Key<Date,Integer> |
EXTENDED_CREATION_DATE
Date used for calculation and reporting.
|
static Key<Date,Integer> |
FINISH_DATE
The finish date of a project.
|
static Key<NullableBool,Integer> |
FISCAL_YEAR_START
Determines whether the fiscal year numbering is used.
|
static Key<Integer,Integer> |
FY_START_DATE
The month when fiscal year is starting.
|
static Key<UUID,Integer> |
GUID
The GUID of the project.
|
static Key<NullableBool,Integer> |
HONOR_CONSTRAINTS
Determines whether tasks honor their constraint dates.
|
static Key<String,Integer> |
HYPERLINK_BASE
Project's hyperlink base.
|
static Key<NullableBool,Integer> |
INSERTED_PROJECTS_LIKE_SUMMARY
Determines whether subtasks are calculated as summary tasks.
|
static Key<NullableBool,Integer> |
KEEP_TASK_ON_NEAREST_WORKING_TIME_WHEN_MADE_AUTO_SCHEDULED
Determines whether manual tasks must be kept on nearest working time when made as auto scheduled.
|
static Key<String,Integer> |
KEYWORDS
Project's keywords.
|
static Key<String,Integer> |
LAST_AUTHOR
Project's last author.
|
static Key<Date,Integer> |
LAST_PRINTED
Project's last print time.
|
static Key<Date,Integer> |
LAST_SAVED
The date when a project was saved last time.
|
static Key<String,Integer> |
MANAGER
The manager of a project.
|
static Key<NullableBool,Integer> |
MICROSOFT_PROJECT_SERVER_URL
Determines whether a project was created by a Project Server user as opposed to an NT user.
|
static Key<Integer,Integer> |
MINUTES_PER_DAY
The number of minutes per day.
|
static Key<Integer,Integer> |
MINUTES_PER_WEEK
The number of minutes per week.
|
static Key<NullableBool,Integer> |
MOVE_COMPLETED_ENDS_BACK
Determines whether the end of completed portions of tasks scheduled to start
after the status date but started earlier should be moved back to the status date.
|
static Key<NullableBool,Integer> |
MOVE_COMPLETED_ENDS_FORWARD
Determines whether the end of completed portions of tasks scheduled
to have been completed before the status date but begun later
should be moved up to the status date.
|
static Key<NullableBool,Integer> |
MOVE_REMAINING_STARTS_BACK
Determines whether the beginning of remaining portions of tasks scheduled to start
after the status date but started earlier should be moved back to the status date.
|
static Key<NullableBool,Integer> |
MOVE_REMAINING_STARTS_FORWARD
Determines whether the beginning of remaining portions of tasks
scheduled to have begun later should be moved up to the status date.
|
static Key<NullableBool,Integer> |
MULTIPLE_CRITICAL_PATHS
Determines whether multiple critical paths are calculated.
|
static Key<String,Integer> |
NAME
The name of the project.
|
static Key<Integer,Integer> |
NEW_TASK_START_DATE
The default start date type for new tasks.
|
static Key<NullableBool,Integer> |
NEW_TASKS_ARE_MANUAL
Determines whether new tasks created as manual.
|
static Key<NullableBool,Integer> |
NEW_TASKS_EFFORT_DRIVEN
Determines whether new tasks are effort driven.
|
static Key<NullableBool,Integer> |
NEW_TASKS_ESTIMATED
Determines whether an estimated duration is shown by default.
|
static Key<NullableBool,Integer> |
PROJECT_EXTERNALLY_EDITED
Determines whether the project was externally edited.
|
static Key<NullableBool,Integer> |
REMOVE_FILE_PROPERTIES
Determines whether all file properties will be removed on save.
|
static Key<Integer,Integer> |
REVISION
The number of times a project was saved.
|
static Key<Integer,Integer> |
SAVE_VERSION
The version of Microsoft Office Project from which a project file was saved.
|
static Key<NullableBool,Integer> |
SCHEDULE_FROM_START
Determines whether to calculate the project schedule forward from the start date.
|
static Key<Boolean,Integer> |
SHOW_PROJECT_SUMMARY_TASK
Determines whether to display summary information about an entire project on a single row with its own summary
task bar at the top of the Gantt Chart view.
|
static Key<NullableBool,Integer> |
SPLITS_IN_PROGRESS_TASKS
Determines whether in-progress tasks can be split.
|
static Key<NullableBool,Integer> |
SPREAD_ACTUAL_COST
Determines whether actual costs are spread to the status date.
|
static Key<NullableBool,Integer> |
SPREAD_PERCENT_COMPLETE
Determines whether a percent complete is spread to the status date.
|
static Key<Date,Integer> |
START_DATE
The start date of a project.
|
static Key<Date,Integer> |
STATUS_DATE
the status date to display progress or to calculate earned value totals.
|
static Key<String,Integer> |
SUBJECT
The subject of a project.
|
static Key<NullableBool,Integer> |
TASK_UPDATES_RESOURCE
Determines whether updates to tasks update resources.
|
static Key<String,Integer> |
TEMPLATE
Project's template.
|
static Key<Date,Integer> |
TIMESCALE_FINISH
The date that the timescale in the view finishes.
|
static Key<Date,Integer> |
TIMESCALE_START
The date that the timescale in the view starts.
|
static Key<String,Integer> |
TITLE
The title of a project.
|
static Key<String,Integer> |
UID
The unique Id of a project.
|
static Key<NullableBool,Integer> |
UPDATE_MANUALLY_SCHEDULED_TASKS_WHEN_EDITING_LINKS
Determines whether manual tasks must be updated when links were edited.
|
static Key<Integer,Integer> |
WEEK_START_DAY
First day of a week.
|
static Key<Integer,Integer> |
WORK_FORMAT
The format used to show the duration of the task.
|
public static final Key<NullableBool,Integer> ACTUALS_IN_SYNC
Determines whether all actual works have been synchronized with the project.
public static final Key<NullableBool,Integer> ADMIN_PROJECT
Determines whether a project is an administrative project.
public static final Key<NullableBool,Integer> ARE_EDITABLE_ACTUAL_COSTS
Determines whether actual costs are editable.
public static final Key<NullableBool,Integer> AUTO_ADD_NEW_RESOURCES_AND_TASKS
Determines whether new resources or tasks automatically added to a resource or task pool.
public static final Key<NullableBool,Integer> AUTOLINK
Determines whether inserted or moved tasks are auto linked.
public static final Key<Integer,Integer> BASELINE_FOR_EARNED_VALUE
The specific baseline used to calculate Variance values.
public static final Key<Integer,Integer> CRITICAL_SLACK_LIMIT
The number of days to the end of a task when Microsoft Project marks that task as a critical task.
public static final Key<String,Integer> CURRENCY_CODE
The three letter currency character code as defined in ISO 4217. Example of valid values is "USD".
public static final Key<Integer,Integer> CURRENCY_DIGITS
The number of digits after a decimal symbol.
public static final Key<String,Integer> CURRENCY_SYMBOL
The currency symbol used in a project.
public static final Key<Integer,Integer> CURRENCY_SYMBOL_POSITION
The placement of the currency symbol.
public static final Key<String,Integer> CUSTOM_DATE_FORMAT
Project view custom date format. Used to format dates when DATE_FORMAT
property is set to DateFormat.Custom
.
public static final Key<Integer,Integer> DAYS_PER_MONTH
The number of days per month.
public static final Key<Date,Integer> DEFAULT_FINISH_TIME
The default finish time of new tasks.
public static final Key<Integer,Integer> DEFAULT_FIXED_COST_ACCRUAL
The default type when fixed costs are accrued.
public static final Key<Double,Integer> DEFAULT_OVERTIME_RATE
The default overtime rate for new resources.
public static final Key<Double,Integer> DEFAULT_STANDARD_RATE
The default standard rate for new resources.
public static final Key<Date,Integer> DEFAULT_START_TIME
The default start time of new tasks.
public static final Key<Integer,Integer> DEFAULT_TASK_EV_METHOD
The default earned value method for tasks.
public static final Key<Integer,Integer> DEFAULT_TASK_TYPE
The default type of new tasks.
public static final Key<Integer,Integer> DURATION_FORMAT
The format for expressing the bulk duration.
TimeUnitType
type.
public static final Key<Integer,Integer> EARNED_VALUE_METHOD
The default method for calculating earned value.
public static final Key<Date,Integer> EXTENDED_CREATION_DATE
Date used for calculation and reporting.
public static final Key<NullableBool,Integer> FISCAL_YEAR_START
Determines whether the fiscal year numbering is used.
public static final Key<Integer,Integer> FY_START_DATE
The month when fiscal year is starting.
public static final Key<NullableBool,Integer> HONOR_CONSTRAINTS
Determines whether tasks honor their constraint dates.
public static final Key<NullableBool,Integer> INSERTED_PROJECTS_LIKE_SUMMARY
Determines whether subtasks are calculated as summary tasks.
public static final Key<NullableBool,Integer> KEEP_TASK_ON_NEAREST_WORKING_TIME_WHEN_MADE_AUTO_SCHEDULED
Determines whether manual tasks must be kept on nearest working time when made as auto scheduled.
public static final Key<NullableBool,Integer> MICROSOFT_PROJECT_SERVER_URL
Determines whether a project was created by a Project Server user as opposed to an NT user.
public static final Key<Integer,Integer> MINUTES_PER_DAY
The number of minutes per day.
public static final Key<Integer,Integer> MINUTES_PER_WEEK
The number of minutes per week.
public static final Key<NullableBool,Integer> MOVE_COMPLETED_ENDS_BACK
Determines whether the end of completed portions of tasks scheduled to start after the status date but started earlier should be moved back to the status date.
public static final Key<NullableBool,Integer> MOVE_COMPLETED_ENDS_FORWARD
Determines whether the end of completed portions of tasks scheduled to have been completed before the status date but begun later should be moved up to the status date.
public static final Key<NullableBool,Integer> MOVE_REMAINING_STARTS_BACK
Determines whether the beginning of remaining portions of tasks scheduled to start after the status date but started earlier should be moved back to the status date.
public static final Key<NullableBool,Integer> MOVE_REMAINING_STARTS_FORWARD
Determines whether the beginning of remaining portions of tasks scheduled to have begun later should be moved up to the status date.
public static final Key<NullableBool,Integer> MULTIPLE_CRITICAL_PATHS
Determines whether multiple critical paths are calculated.
public static final Key<NullableBool,Integer> NEW_TASKS_ARE_MANUAL
Determines whether new tasks created as manual.
public static final Key<NullableBool,Integer> NEW_TASKS_EFFORT_DRIVEN
Determines whether new tasks are effort driven.
public static final Key<NullableBool,Integer> NEW_TASKS_ESTIMATED
Determines whether an estimated duration is shown by default.
public static final Key<Integer,Integer> NEW_TASK_START_DATE
The default start date type for new tasks.
public static final Key<NullableBool,Integer> PROJECT_EXTERNALLY_EDITED
Determines whether the project was externally edited.
public static final Key<NullableBool,Integer> REMOVE_FILE_PROPERTIES
Determines whether all file properties will be removed on save.
public static final Key<Integer,Integer> SAVE_VERSION
The version of Microsoft Office Project from which a project file was saved.
public static final Key<NullableBool,Integer> SCHEDULE_FROM_START
Determines whether to calculate the project schedule forward from the start date.
public static final Key<Boolean,Integer> SHOW_PROJECT_SUMMARY_TASK
Determines whether to display summary information about an entire project on a single row with its own summary task bar at the top of the Gantt Chart view.
public static final Key<NullableBool,Integer> SPLITS_IN_PROGRESS_TASKS
Determines whether in-progress tasks can be split.
public static final Key<NullableBool,Integer> SPREAD_ACTUAL_COST
Determines whether actual costs are spread to the status date.
public static final Key<NullableBool,Integer> SPREAD_PERCENT_COMPLETE
Determines whether a percent complete is spread to the status date.
public static final Key<Date,Integer> STATUS_DATE
the status date to display progress or to calculate earned value totals. The status date is the same as the current date (today's date) unless a different status date is specified.
public static final Key<NullableBool,Integer> TASK_UPDATES_RESOURCE
Determines whether updates to tasks update resources.
public static final Key<Date,Integer> TIMESCALE_FINISH
The date that the timescale in the view finishes.
public static final Key<Date,Integer> TIMESCALE_START
The date that the timescale in the view starts.
public static final Key<NullableBool,Integer> UPDATE_MANUALLY_SCHEDULED_TASKS_WHEN_EDITING_LINKS
Determines whether manual tasks must be updated when links were edited.
public static final Key<Integer,Integer> WORK_FORMAT
The format used to show the duration of the task.
Copyright (c) 2008-2020 Aspose Pty Ltd. All Rights Reserved.