Class ReportType
- java.lang.Object
-
- com.aspose.ms.System.ValueType<com.aspose.ms.System.Enum>
-
- com.aspose.ms.System.Enum
-
- com.aspose.tasks.ReportType
-
public final class ReportType extends com.aspose.ms.System.Enum
Type of the project's graphical report.
-
-
Field Summary
Fields Modifier and Type Field Description static int
BestPracticeAnalyzer
Shows tasks with no actual work, not assigned tasks, tasks with duration less than 8 hours and summaries assigned with the resources.static int
Burndown
Includes work burndown and task burndown charts.static int
CashFlow
Shows the costs and cumulative costs per quarter for all top-level tasks.static int
CostOverruns
Shows cost variance by task and resource.static int
CostOverview
Shows the project’s start and finish dates, the current scheduled and remaining cost, % Complete and cost values for top-level tasks.static int
CriticalTasks
Shows project tasks that are critical.static int
LateTasks
Shows project tasks that are late.static int
Milestones
Shows milestones that are late, coming up and completed.static int
OverallocatedResources
Shows the number of remaining work hours for over allocated resources.static int
ProjectOverview
Shows the project’s start and finish date, percentage of duration that’s complete, percentage complete for top-level tasks and coming up milestones.static int
ResourceCostOverview
Shows baseline, actual, and remaining cost by resource.static int
ResourceOverview
Shows baseline, actual, and remaining work by resource.static int
SlippingTasks
Shows tasks that are due to finish after their baseline finish dates (baseline must be setInternal).static int
TaskCostOverview
Shows baseline, actual, and remaining cost of all top-level tasks.static int
UpcomingTask
Shows tasks that are due during the current week and tasks starting during current week.static int
WorkOverview
Shows baseline, actual, remaining work for each top-level task and work for work resources.
-
Method Summary
-
Methods inherited from class com.aspose.ms.System.Enum
Clone, CloneTo, format, format, get_Caption, get_Value, getName, getName, getNames, getNames, getUnderlyingType, getUnderlyingType, getValue, getValues, isDefined, isDefined, isDefined, isDefined, parse, parse, parse, parse, register, toObject, toString
-
-
-
-
Field Detail
-
ProjectOverview
public static final int ProjectOverview
Shows the project’s start and finish date, percentage of duration that’s complete, percentage complete for top-level tasks and coming up milestones.
- See Also:
- Constant Field Values
-
CostOverview
public static final int CostOverview
Shows the project’s start and finish dates, the current scheduled and remaining cost, % Complete and cost values for top-level tasks.
- See Also:
- Constant Field Values
-
WorkOverview
public static final int WorkOverview
Shows baseline, actual, remaining work for each top-level task and work for work resources.
- See Also:
- Constant Field Values
-
ResourceOverview
public static final int ResourceOverview
Shows baseline, actual, and remaining work by resource.
- See Also:
- Constant Field Values
-
ResourceCostOverview
public static final int ResourceCostOverview
Shows baseline, actual, and remaining cost by resource.
- See Also:
- Constant Field Values
-
CriticalTasks
public static final int CriticalTasks
Shows project tasks that are critical.
- See Also:
- Constant Field Values
-
LateTasks
public static final int LateTasks
Shows project tasks that are late.
- See Also:
- Constant Field Values
-
Milestones
public static final int Milestones
Shows milestones that are late, coming up and completed.
- See Also:
- Constant Field Values
-
UpcomingTask
public static final int UpcomingTask
Shows tasks that are due during the current week and tasks starting during current week.
- See Also:
- Constant Field Values
-
CostOverruns
public static final int CostOverruns
Shows cost variance by task and resource.
- See Also:
- Constant Field Values
-
TaskCostOverview
public static final int TaskCostOverview
Shows baseline, actual, and remaining cost of all top-level tasks.
- See Also:
- Constant Field Values
-
OverallocatedResources
public static final int OverallocatedResources
Shows the number of remaining work hours for over allocated resources.
- See Also:
- Constant Field Values
-
SlippingTasks
public static final int SlippingTasks
Shows tasks that are due to finish after their baseline finish dates (baseline must be setInternal).
- See Also:
- Constant Field Values
-
BestPracticeAnalyzer
public static final int BestPracticeAnalyzer
Shows tasks with no actual work, not assigned tasks, tasks with duration less than 8 hours and summaries assigned with the resources.
- See Also:
- Constant Field Values
-
Burndown
public static final int Burndown
Includes work burndown and task burndown charts. The work burndown chart shows how much work people have finished, how much is scheduled to be finished before the project finish date, and the baseline estimate of how much work would be completed at this point in the project. The task burndown chart shows the number of tasks finished, the number remaining, and the baseline estimate of how many would be finished at this point in the project.
- See Also:
- Constant Field Values
-
CashFlow
public static final int CashFlow
Shows the costs and cumulative costs per quarter for all top-level tasks.
- See Also:
- Constant Field Values
-
-