static Key<NullableBool,Integer> |
Prj.ACTUALS_IN_SYNC |
Determines whether all actual works have been synchronized with the project.
|
static Key<NullableBool,Integer> |
Prj.ADMIN_PROJECT |
Determines whether a project is an administrative project.
|
static Key<NullableBool,Integer> |
Prj.ARE_EDITABLE_ACTUAL_COSTS |
Determines whether actual costs are editable.
|
static Key<NullableBool,Integer> |
Prj.AUTO_ADD_NEW_RESOURCES_AND_TASKS |
Determines whether new resources or tasks automatically added to a resource or task pool.
|
static Key<NullableBool,Integer> |
Prj.AUTOLINK |
Determines whether inserted or moved tasks are auto linked.
|
static Key<NullableBool,Integer> |
Rsc.CAN_LEVEL |
Determines whether resource leveling can be done on a resource.
|
static Key<NullableBool,Integer> |
Tsk.DISPLAY_AS_SUMMARY |
Determines whether the task should be displayed as a summary task.
|
static Key<NullableBool,Integer> |
Prj.FISCAL_YEAR_START |
Determines whether the fiscal year numbering is used.
|
static Key<NullableBool,Integer> |
Tsk.HAS_OVERALLOCATED_RESOURCE |
Indicates whether the task has an resource assigned which has more work on assigned tasks than can be completed
within normal working capacity.
|
static Key<NullableBool,Integer> |
Tsk.HIDE_BAR |
Determines whether the Gantt bar of a task is hidden when displayed in Microsoft Project.
|
static Key<NullableBool,Integer> |
Prj.HONOR_CONSTRAINTS |
Determines whether tasks honor their constraint dates.
|
static Key<NullableBool,Integer> |
Tsk.IGNORE_RESOURCE_CALENDAR |
Determines whether the scheduling of the task considers the calendars of the resources assigned to the task.
|
static Key<NullableBool,Integer> |
Rsc.INACTIVE |
Determines whether a resource was made inactive by a user who has administrative rights.
|
static Key<NullableBool,Integer> |
Prj.INSERTED_PROJECTS_LIKE_SUMMARY |
Determines whether subtasks are calculated as summary tasks.
|
static Key<NullableBool,Integer> |
Tsk.IS_ACTIVE |
Determines whether a task is active.
|
static Key<NullableBool,Integer> |
Rsc.IS_BUDGET |
Determines whether a work, material, or cost resource is a budget resource.
|
static Key<NullableBool,Integer> |
Rsc.IS_COST_RESOURCE |
Determines whether a resource is a cost resource.
|
static Key<NullableBool,Integer> |
Tsk.IS_CRITICAL |
Determines whether a task is on the critical path.
|
static Key<NullableBool,Integer> |
Tsk.IS_EFFORT_DRIVEN |
Determines whether the scheduling for the task is effort-driven scheduling.
|
static Key<NullableBool,Integer> |
Rsc.IS_ENTERPRISE |
Shows whether a resource is from the enterprise resource pool (true) or the local resource pool (false).
|
static Key<NullableBool,Integer> |
Tsk.IS_ESTIMATED |
Determines whether a task is estimated.
|
static Key<NullableBool,Integer> |
Tsk.IS_EXPANDED |
Determines whether a summary task is expanded or not in GanttChart view.
|
static Key<NullableBool,Integer> |
Rsc.IS_GENERIC |
Determines whether a resource is generic or not.
|
static Key<NullableBool,Integer> |
Tsk.IS_MANUAL |
Determines whether a task is manually scheduled.
|
static Key<NullableBool,Integer> |
Tsk.IS_MILESTONE |
Determines whether a task is a milestone.
|
static Key<NullableBool,Integer> |
Rsc.IS_NULL |
Determines whether a resource is null.
|
static Key<NullableBool,Integer> |
Tsk.IS_NULL |
Determines whether a task is a null task.
|
static Key<NullableBool,Integer> |
Tsk.IS_OVERALLOCATED |
Indicates whether any of the assigned resources on a task is assigned to more work on the task than can be done
withing the normal working capacity.
|
static Key<NullableBool,Integer> |
Tsk.IS_PUBLISHED |
Determines whether the current task should be published to Project Server with the rest of the project.
|
static Key<NullableBool,Integer> |
Tsk.IS_RECURRING |
Determines whether a task is part of a series of recurring tasks.
|
static Key<NullableBool,Integer> |
Tsk.IS_RESUME_VALID |
Determines whether a task can be resumed.
|
static Key<NullableBool,Integer> |
Tsk.IS_ROLLUP |
Determines whether information about the subtask Gantt bars will be rolled up to the summary task bar.
|
static Key<NullableBool,Integer> |
Tsk.IS_SUBPROJECT_READ_ONLY |
Determines whether a subproject is read-only.
|
static Key<NullableBool,Integer> |
Prj.KEEP_TASK_ON_NEAREST_WORKING_TIME_WHEN_MADE_AUTO_SCHEDULED |
Determines whether manual tasks must be kept on nearest working time when made as auto scheduled.
|
static Key<NullableBool,Integer> |
Tsk.LEVEL_ASSIGNMENTS |
Determines whether the leveling function can delay and split individual assignments in order to resolve over
allocations.
|
static Key<NullableBool,Integer> |
Tsk.LEVELING_CAN_SPLIT |
Determines whether the resource leveling function can cause splits on remaining work on this task.
|
static Key<NullableBool,Integer> |
Prj.MICROSOFT_PROJECT_SERVER_URL |
Determines whether a project was created by a Project Server user as opposed to an NT user.
|
static Key<NullableBool,Integer> |
Prj.MOVE_COMPLETED_ENDS_BACK |
Determines whether the end of completed portions of tasks scheduled to start
after the status date but started earlier should be moved back to the status date.
|
static Key<NullableBool,Integer> |
Prj.MOVE_COMPLETED_ENDS_FORWARD |
Determines whether the end of completed portions of tasks scheduled
to have been completed before the status date but begun later
should be moved up to the status date.
|
static Key<NullableBool,Integer> |
Prj.MOVE_REMAINING_STARTS_BACK |
Determines whether the beginning of remaining portions of tasks scheduled to start
after the status date but started earlier should be moved back to the status date.
|
static Key<NullableBool,Integer> |
Prj.MOVE_REMAINING_STARTS_FORWARD |
Determines whether the beginning of remaining portions of tasks
scheduled to have begun later should be moved up to the status date.
|
static Key<NullableBool,Integer> |
Prj.MULTIPLE_CRITICAL_PATHS |
Determines whether multiple critical paths are calculated.
|
static Key<NullableBool,Integer> |
Prj.NEW_TASKS_ARE_MANUAL |
Determines whether new tasks created as manual.
|
static Key<NullableBool,Integer> |
Prj.NEW_TASKS_EFFORT_DRIVEN |
Determines whether new tasks are effort driven.
|
static Key<NullableBool,Integer> |
Prj.NEW_TASKS_ESTIMATED |
Determines whether an estimated duration is shown by default.
|
static Key<NullableBool,Integer> |
Rsc.OVERALLOCATED |
Indicates whether a resource is assigned to more work on a specific task or all tasks than can be completed
within normal working capacity.
|
static Key<NullableBool,Integer> |
Prj.PROJECT_EXTERNALLY_EDITED |
Determines whether the project was externally edited.
|
static Key<NullableBool,Integer> |
Prj.REMOVE_FILE_PROPERTIES |
Determines whether all file properties will be removed on save.
|
static Key<NullableBool,Integer> |
Prj.SCHEDULE_FROM_START |
Determines whether to calculate the project schedule forward from the start date.
|
static Key<NullableBool,Integer> |
Prj.SPLITS_IN_PROGRESS_TASKS |
Determines whether in-progress tasks can be split.
|
static Key<NullableBool,Integer> |
Prj.SPREAD_ACTUAL_COST |
Determines whether actual costs are spread to the status date.
|
static Key<NullableBool,Integer> |
Prj.SPREAD_PERCENT_COMPLETE |
Determines whether a percent complete is spread to the status date.
|
static Key<NullableBool,Integer> |
Prj.TASK_UPDATES_RESOURCE |
Determines whether updates to tasks update resources.
|
static Key<NullableBool,Integer> |
Prj.UPDATE_MANUALLY_SCHEDULED_TASKS_WHEN_EDITING_LINKS |
Determines whether manual tasks must be updated when links were edited.
|