KeySummaryIssue Type
TASKSNET-11701Fix incorrect recalculation of Actual Work timephased data when changing resource base calendar and adding exceptionsBug
TASKSNET-11699Fix incorrect calculation of summary tasks after modification of Task.FinishBug
TASKSNET-11698Fix incorrect cascading recalculation of ‘% complete’ and ‘% work complete’ fieldsBug
TASKSNET-11685Fix actual work distribution is changed when calendar exception is added to the calendarBug
TASKSNET-11681Fix reading of values of enterprise extended attribute with type = Cost for the specific fileBug
TASKSNET-11668Fix writing of Outline Code values to MPPBug
TASKSNET-11590Fix assignments not aligned with parent task become aligned after changing task durationBug
TASKSNET-11574Fix actual assignment work TD is corrupted when task calendar is modifiedBug