⚠ IMPORTANT DEPRECATION NOTICE
Starting with version 26.10, support for JDK 1.7 will be completely discontinued.
What is changing:
- The minimum supported Java version will be JDK 1.8 (Java 8) or higher.
- JDK 1.7 will no longer be compatible with the product.
Recommended actions:
Please plan to migrate your environments and deployment scripts to JDK 1.8 or higher to avoid failures when upgrading to version 26.10.
The current version (up to 26.9 inclusive) continues to work with JDK 1.7, but we strongly recommend starting the migration process now.
All Changes
| Key | Summary | Issue Type |
|---|---|---|
| TASKSNET-11701 | Fix incorrect recalculation of Actual Work timephased data when changing resource base calendar and adding exceptions | Bug |
| TASKSNET-11699 | Fix incorrect calculation of summary tasks after modification of Task.Finish | Bug |
| TASKSNET-11698 | Fix incorrect cascading recalculation of ‘% complete’ and ‘% work complete’ fields | Bug |
| TASKSNET-11685 | Fix actual work distribution is changed when calendar exception is added to the calendar | Bug |
| TASKSNET-11681 | Fix reading of values of enterprise extended attribute with type = Cost for the specific file | Bug |
| TASKSNET-11668 | Fix writing of Outline Code values to MPP | Bug |
| TASKSNET-11590 | Fix assignments not aligned with parent task become aligned after changing task duration | Bug |
| TASKSNET-11574 | Fix actual assignment work TD is corrupted when task calendar is modified | Bug |
| TASKSNET-11158 | Fix MS Project removes split when recalculating project containing non-working split between Stop and Resume dates | Bug |
| TASKSJAVA-2393 | Adding calendar exceptions changes Actual Work distribution after save | Bug |
| TASKSJAVA-2394 | Changing resource base calendar and adding exceptions shifts Resume time and alters Actual Work | Bug |